Wednesday 27 March 2013

3rd Floor Slab in Place

Today is 27th March 2013.

Formwork for columns in process with steel reinforced bars ready to be enclosed with formwork. Expected delay due architects drawings in error. Called architect and they are supposed to come to the site tommorrow.