Wednesday, 22 May 2013

The foot print of an antenna tower

The 4 screws attached to the concrete slab on the roof of the masterbedroom.
These screws were first welded onto a steel plate which was fastened to the steel bars which form the reinforcement of the 150mm conrete slab - all done while the concrete was being poured into the formwork.

Wednesday, 27 March 2013

3rd Floor Slab in Place

Today is 27th March 2013.

Formwork for columns in process with steel reinforced bars ready to be enclosed with formwork. Expected delay due architects drawings in error. Called architect and they are supposed to come to the site tommorrow.